轨道交通大断面地下暗挖工程施工风险分析与控制
XXX XXX
1
2
1. 上海建科工程咨询有限公司,上海,200032 2. 上海建科工程咨询有限公司,上海,200032
摘要:伴随着经济的迅猛发展,我国地铁建设迎来了飞速发展的时期。由于地铁工程所处地层工程地质条件、水文地质条件及工程环境的复杂性,不可预见因素较多,其工程施工风险较大。本文以青岛地铁一期工程(3号线)君峰路站为例,采用基于层次分析法(AHP)与专家打分法的综合集成风险评估法,对车站施工全过程的风险因素进行分析,并针对重大风险源提出相应的风险控制措施。
关键词:暗挖工程;层次分析法;风险分析;风险控制
Abstract:Along with the rapid development of economy, China’s metro construction has ushered in a period of fast development.As the complexity of its Engineering geological conditions, hydrogeological conditions and environmental engineering,there are many unforeseen factors which greatly increase risks of construction ingIntegrated risk assessment method based on analytic hierarchy process(AHP) and expert evaluation method,this paper, takingJunfenglu Station in Qingdao Metro Project (Line 3) as an example,analyzes all the risk factors in the whole constructionprocess,and proposes corresponding risk control methods against major risks.
Keyword:Excavation engineering; analytic hierarchy process(AHP);risk analysis;risk control
1引言
随着经济的高速发展,我国城市化进程不断加快,人口逐渐向城镇集中。人口的急剧增加对城市交通系统的压力日益增大,人民群众对城市交通系统改造的呼声越来越高。发达国家大城市发展的经验教训说明,地下空间与上部空间协调发展,充分利用地下空间是城市交通系统改造最有效的途径。地铁的建设将是我国21世纪城市地下空间开发的重点。
地铁隧道一般都处于城市中心交通繁忙、环境复杂的地段,具有其独特不确定性与复杂性。地铁工程从规划设计、施工建设到竣工运营每个阶段的风险都会引起巨大的损失。为规范地铁工程建设风险管理,有效控制工程建设风险,减少各类风险事故的发生,对地铁隧道施工过程中的各类风险进行有效评估,以控制、规避各种风险的发生显得尤为重要。本文以青岛地铁一期工程(3号线)君峰路站为例,简单介绍地铁隧道建设中常用的风险分析方法,并详细分析本站可能发生的各种风险,并针对其重大风险源给出具体的风险控制措施。
2 工程概况
青岛地铁一期工程(3号线)君峰路站位于京口路与君峰路的交汇处,沿京口路一字型布置,西北-东南走向。车站两端地形东高西低,沿线建筑多为多层建筑,站址范围内地质条件较好,岩面较高。京口路南侧有埋深 4.075m的6孔电信管,埋深4.875m的 300mm污水管,埋深4.57m的800mm 雨水管,其余管线埋深较浅。
车站地貌为侵蚀堆积一级阶地、剥蚀堆积缓坡。第四系不发育,局部可见基岩裸露。地貌成因类型为剥蚀残丘,围岩级别III~IV级,场区内表覆第四系全新统人工堆积层素填土,下伏燕山晚期粗粒花岗岩,局部穿插有煌斑岩等脉岩。场区的地下水主要为风化裂隙水和构造裂隙水。
车站为地下二层岛式车站,采用马蹄形单拱双层复合式衬砌断面;共设4个出入口通道,