PMP考试模拟题(683个)-v2(15)

发布时间:2021-06-08   来源:未知    
字号:

PMP需要参考

29BActivities29CSlack elements.29DB and C only.29EAll of the above.29

210QUESTActivities with zero time duration are referred to as:210ACritical path activites.210BNoncritical path activities.210CSlack time activities.210DDummies210ENone of above.210

211QUESTIn the PDM, common constraints include:211AStart-to-start211BFinish-to-start211CFinish-to-finish211DB and C only211EA, B, and C.211

QUESTWhich of the following networking methods allows us to show that the last 10% of one element

212

cannot be completed until 62% of a previous element has been completed?212APERT212BADM212CPDM212DAll of the above.212EA and C only.212

213QUESTGuidelines for estimating time durations include:213AAssuming a normal level of labor and equipment.213BAssuming a normal work week.213CUsing consistent time units213DUsing past actual durations as guides.213EAll or part of each of the above.213

214QUESTSmoothing out resource requirements from period to period is called resource _____.214AAllocation.214BPartitioning214CLeveling.214DQuantification214ENone of above.214

QUESTAssigning resources in an attempt to find the shortest project schedule consistent with fixed

215

resource limits is called resource _____.215AAllocation.215BPartitioning215CLeveling215DQuantification.215ENone of above.215

QUESTIn general, attempts to smooth out period to period resources will _____ the scheduled time and

216

_____ project costs.216AIncrease, decrease.216BIncrease, increase216CIncrease, increase or decrease.216DDecrease, decrease.216EDecrease, increase.216

217QUESTWhich method shown below is acceptable for reducing cost or shortening the schedule?217A"Crashing"217BChanging scope.

A

D

E

C

E

C

A

B

PMP考试模拟题(683个)-v2(15).doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印
×
二维码
× 游客快捷下载通道(下载后可以自由复制和排版)
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
注:下载文档有可能出现无法下载或内容有问题,请联系客服协助您处理。
× 常见问题(客服时间:周一到周五 9:30-18:00)