222222251QUESTResource leveling will often affect the project by making it:51AShorter.51BLonger51CMore responsive to customer needs.51DA and C51EB and C.51
QUESTA plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks.
B
252
Calculate the variance:252A1.50%252B33.00%252C75%252D67%252ENone of the above.252
QUESTOn November 1, $1000 worth of work on task A was supposed to have been done (BCWS);
253
however, the BCWP was $850. Calculate the schedule variance:253A¥-100253B¥100253C¥-150253D¥150253E85%253
254QUESTThe purpose of a dummy activity in an activity-on-arrow diagram is to:254AIdentify a task that could be replaced by another.254BTake the slack time into account.254CShow a task that is not necessarily needed.254DDenote a milestone.254EShow a dependency relationship.254
QUESTAs a project is carried out and slack time is consumed on individual tasks, the slack left over for
255
the remaining tasks is:255AInsignificant.255BReduced.255CUnchanged.255DIncreased.255EDoubled.255
256QUESTFast tracking means to:256ASpeed up a project through parallel tasks.256BSwap one task for another.256CReduce the number of tasks if possible.256DB and C.256ENone of the above.256
257QUESTThe key purpose of project control is to:257APlan ahead for uncertainties.257BGenerate status reports.257CKeep the project on track.257DDevelop the project road map.257EAll of the above.257
258QUESTExcessive flexibility in specifying requirements will _____ the likelihood of time overruns.258AReduce.258BEliminate.258CDouble
B
C
E
C
A
C