PMP考试模拟题(683个)-v2(17)

发布时间:2021-06-08   来源:未知    
字号:

PMP需要参考

226

227QUESTThe starting point in the development of a top-down PERT/CPM chart is the _____ .227AProject specification tree.227BCustomer's deliverable list.227CCustomer's milestone dates.227DWork breakdown structure.227EListing of customer team meeting dates.227

228QUESTADM is an activity-on-arrow method. In this method, a dummy activity:228ADenotes a critical path relationship.228BDenotes any dependency relationship.228CShows slack.228DIdentifies customer deliverables dates.228EIdentifies customer team meeting dates.2

28

QUESTOnce the logic of a network is laid out, the project manager will conduct a forward pass and

backward pass through the network. This will provide information on the _____ and identification229

of the _____ .229ASlack for each activity, critical path.229BSlack for each activity, high risk activities.229CManpower shortages, high risk activities.229DHigh risk activities, non-critical paths.229EManpower availability, contingency plans.229

230QUESTA non-critical path activity is completed in half the time. Then,230AThe critical path is also reduced.230BThe slack in the path containing this activity will increase.230CThe total cost for this activity has decreased.230DManpower from this activity can be assigned to other activities.230EAll of the above.230

231QUESTBar charts are most appropriate for:231AComparing actual to planned performance to each activity.231BShowing slack time.231CShowing critical path dependencies.231DShowing which activities can be rearranged in parallel.231EAll of the above.2

31

QUESTA network has been developed with resources from six different departments. One of the six

departments has just informed you that they can increase the number of employees from 5 to 8.232

This will result in:232AA shortening of the critical path.232BA shortening of the noncritical path.232CA decrease in the total cost of the project.232DAn increase in the cost of the project.232EA through D are possible based upon where the resources are deployed.232

QUESTManagement has decided to "crash" a project in order to avoid penalty payments for late

233

deliveries. To crash the project, either overtime or additional resources should be assigned to:233AAll activities.233BOnly those activities with the longest time durations.233CThose activities on the critical path begining with the longest time duration activities.233DThose activities with the greatest degree of risk.233ENone of the above.2

33

QUESTA line manager provides you with three estimates for his activity in your PERT network. His

estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The235

expected time which would appear on the chart would be:235A4 weeks2

35B5 weeks

B

D

B

A

B

A

E

C

PMP考试模拟题(683个)-v2(17).doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印
×
二维码
× 游客快捷下载通道(下载后可以自由复制和排版)
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
注:下载文档有可能出现无法下载或内容有问题,请联系客服协助您处理。
× 常见问题(客服时间:周一到周五 9:30-18:00)